Item | Project title | SR-124 NETWORK REAL TIME MONITIRING PHASE II |
1 | Client | ASHGAL-Public Works Authority |
2 | Consultant | PARSONS International Limited |
3 | Main Contractor | Metito Overseas WLL |
4 | Sub contractor | ALSONAR trading and contracting WLL |
5 | Project Discerption | Underground tank with 100m X 35m X 9.6m height |
6 | Project Duration | 9 months |